Temporary $110,000 bridge OK’d for Urbanna marina

The Urbanna Town Council voted on Aug. 27 to spend $110,000 for a temporary Urbanna Town Marina bridge.

bridge
Building a bridge to the Urbanna Town Marina is complicated by unstable soil on both sides of it. The bridge has been closed to motor vehicle traffic since December. (Photo by Tom Chillemi)

The town received three bids for the temporary bridge. Council chose the bid by Faulconer Construction Company Inc. of Charlottesville, which anticipates starting work Sept. 8. The project is estimated to take three days.

The bridge was designed by the Timmons Group of Richmond. It is certified to support fire trucks and vehicles up to 45,000 pounds (22.5 tons), said Urbanna Mayor Robbie Wilson.